CUSTOMS, EXCISE &
SERVICE TAX APPELLATE TRIBUNAL
WEST BLOCK 2. R.K. PURAM, NEW DELHI
Date of Hearing : 15.12.2003
Date of Decision : 01.07.204
Appeal No. C/601/2001
NB(A)
Arising out of order
in original No.11/Cus/2001 Dated : 25.10.2001 passed by Commissioner of
Customs, Pune
Appeal No.
C/519/2000-NB
Arising out of order
in appeal No. CUS/NK-/2000 Dated : 26.06.2000 Passed by the Commissioner of
Customs (Appeals) Pune.
M/s DABHOL POWER
COMPANY
Vs
CC, PUNE
Appellant :
Rep. by Shri P. Parathasarathy, Adv.
and Shri V.Lakshmikumaran, Adv.
Respondent : Rep. by Shri M. Chandra Sekharan, Sr Adv
with Shri Monish Pushkarna, Advocate
Appeal No.
1C/520/2000-NB (A)
Arising out of order
in appeal No. CUS/NK-330/2000 Dated : 26.2000 passed by Commissioner of Customs
(Appeals), Pune
CC PUNE
Vs
M/s DABHOL POWER
COMPANY
Appellant :
Rep. by Shri M. Chandra Sekharan, Sr. Adv.
with Shri Monish Pushkarna Advocate
Respondent : Rep. by Shri V. Lakshmikumaran, Adv. and
Shri R. Parathasarathy, Advocate
CORAM :
Hon'ble Justice Smt. K.K.
Usha, President
Shri C.N.B. Nair, Member (Technical)
FINAL ORDER NO .
657-659/04-NB(A) Dated : 01.07.2004
Per : Justice K.K. Usha :
Appeal No. C/601/2001 filed by the
importer M/s. Dhabol Power Co. (DPC) is directed against order passed by the
Commissioner of Customs, Pune dated 25.10.2001. Appeal No.C/519/2000 at the
instance of DPC and Appeal No.C/520/2002 at the instance of Chief Commissioner
of Customs, Pune are against the order passed by the Commissioner of Customs
(Appeals), Pune dated 26.6.2000. Since the issues in the above appeals are
inter linked and the imports which are subject matter of the appeals are made
by DPC, we heard the appeals together and they are being disposed of under a
common order.
Under order dated 25.10.2001 the Commissioner
held that the various items of equipment, machinery etc. imported for the
Liquefied Natural Gas (for short, LNG) facility are not entitled to assessment
under Tariff Item 9801.00 (3) as well as under Tariff Item 9801.00 (1) as
project imports. It was also held that a portion of the value of the off-shore
services contract is liable to be added to the declared value of the equipment
etc. imported for the LNG facility. On the above basis provisional assessment
was finalized and demand of duty of Rs. 245,58.73,987/- was upheld on imports
effected and cleared under 319 Bills of entry. There is also a demand of
Rs.8,30,94,084/- in respect of certain goods that have been assessed
provisionally but are pending clearance and a demand of Rs. 21,44,77,666/- on items
imported under 63 Bills of Entry that are pending assessment and clearance. The
learned Commissioner also held that all items imported for LNG facility are
liable for confiscation under Section 11(m) of the Customs Act, 1962 for
alleged mis-declaration and he imposed redemption fine in lieu of confiscation
of an amount of Rs. 1,33,54,841/- on items which are pending
clearance/assessment. He further imposed a penalty of Rs. 45 crores on the
importer/appellant under Section 112(a) of Customs Act, 1962.
In Revenue's appeal No.C/520/2000
challenge is against an order passed on appeal filed by DPC against an
adjudication order passed by Commissioner (Appeals), Pune dated 26.06.2000 on
an appeal filed by DPC against adjudication order passed by the Assistant Commissioner
of Customs, Dapoli Division dated 15.01.99. Under the above order the
adjudicating authority took the view that various machinery and equipment
imported for Single Point Mooring (SPM) system are not covered under Heading
9801.00 as a project import and a differential Customs duty of
Rs.33,29,22,069/- was demanded. It was held that SPM system which was a system
of unloading of fuel from tanker and transporting it to fuel storage tanks
installed at the project site is not integrated to the project of generation of
power. He also took note of the fact that power project ultimately is to be
fueled by LNG facility for which a separate LNG facility was being constructed
and therefore, at the second stage SPM system will normally he idle. It has
only the function of temporary facility and therefore not an integral part of
power project. On appeal the Commissioner took the view that SPM system attains
the character of integral part of the project approved by various sponsoring
authorities and which has been registered in 1996 under Project Import
Regulation, 1986 without any objection. According to the Commissioner (Appeals)
as a result of the restrictions imposed by the Government of India that the
appellant should not use the infrastructure facilities of public sector
canalizing agencies and existing port infrastructure for the import of fuel,
they were compelled to find a source of supply fuel which has to be imported
and this could be done only with the help of SPM system. Therefore, according
to him, the SPM system became a part and parcel of the project. He also took
the view that having registered the project under Project Regulation, 1986 it
would qualify for classification under Chapter 98.01. Taking into consideration
the submission made by the appellants that even after commissioning of Phase
II, SPM would not remain idle and would be used as back up system, the
Commissioner took the view that SPM system would qualify for project import as
an auxiliary system or an integral part of the project. However, after holding
as above, the Commissioner remanded the matter to the adjudicating authority
with a direction "to consider the assessment of SPM appropriately while
finalizing the provisional assessment after examining its role in the second phase
and thereafter decide the matter appropriately". The Revenue has come in
appeal C/520/2000 against the above order contending that finding entered by
the Commissioner (Appeals) that SPM system would qualify for project import as
an auxiliary system for an integral part of the project, cannot be sustained.
DPC has filed appeal No.C/519/2000 challenging that part of the order of the
Commissioner where he remands the case directing Assistant Commissioner to
finalize the provisional assessment of SPM after considering its note in the
second phase.
We will first take up appeal
No.C/601/2001 filed by DPC. The issues coming up for consideration are-
(a)
Whether the various items of equipment, machinery etc. imported for LNG
facility are entitled to the concessional rate of Customs duty under Tariff
Item 9801.0 Project Imports?
(b)
Whether a portion of the value of the Off-shore Services Contract is liable to
be added to the declared value of the equipment under Rule 9(1) (b)(iv) of the
Customs Valuation Rules, 1988? and
(c)
Whether the provisions of Section 111(m) and 112 are attracted to the facts of
the present case?
On the first issue the Commissioner came
to the conclusion that the materials, equipment and machinery for setting up
the LNG facility will not be covered under Tariff Heading 9801.00(3) and
therefore, are entitled to concessional rate of duty for project import. He
also held that machinery and material imported for LNG facility are not
required for substantial expansion of an existing unit of specified power
project. According to the Commissioner, LNG facility is an independent fuel
venture. The Phase I of the power project had been generating power independent
of LNG facility. Even Phase II the power project is capable of generating power
with Naphtha/Distillate had already been constructed for catering to the phase
II of the power project. He further held that LNG facility cannot be considered
as auxiliary equipment of the power project for the purpose of Tariff Heading
9801.0 inasmuch as Tariff Heading does not deal with the auxiliary equipment
required in connection with substantial expansion of the existing unit of the
power project. Tariff Heading covers only auxiliary equipment required for
substantial expansion etc. Reliance was then placed on the decision of this
Tribunal in NALCO 1997 (94) ELT 409 = (2002-TIOL-138-CESTAT-DEL-LB). The alternate submissions
made by the assessee that LNG facility has to be covered as an independent
industrial plant, was also rejected by the Commissioner.
It is contended on behalf of the
appellant that the above finding of the Commissioner is not liable to be sustained.
A memorandum of understanding was executed on 20.06.92 amongst the Maharasthra
State Electricity Board (MSEB), Enron Power Corporation (EPC) and General
Electric Corporation (GEC). The above document outlined in general terms
agreement between the parties for the power development, purchase and sale
contract, design, construction, operation and ownership of an independent power
generating facility at Dabhol with a minimum capacity of 2000 MW. The agreement
contemplated the establishment of a joint venture Company named 'Dabhol Power
Company' (DPC). The power plant will have generating facility of 2000-2400 MW
nominal capacity. It also mentioned "Project includes construction of
regasification facilities for LNG and pipeline interconnections to power plant.
According to the appellant, since this is the first power generation facility
to work on LNG and LNG is not available in India it had to be imported. The
setting up of an LNG facility is an integral part of power plant. Referring to
its letter dated 28th August 1992 seeking approval of the Government of India
for setting up of the project the appellant would contend that proposal to FIPB
was a consolidated proposal that included setting up of LNG facility as a part
and parcel of the power project. The cost of LNG was identified separately as
845 million US$. It is submitted that the above aspects formed part of the
project report submitted to FIPB. Paragraph 1.06.02 referred to initial use of
fuel oil for the power station till the availability of externally sourced LNG.
Letter dated 3.2.93 from FIPB conveying the approval of Government of India for
setting up of the power project at Dabhol would also show that it was an
integrated project including LNG facility.
Subsequently, the approval was modified by
FIPB under communication dated 23.03.94. Pursuant thereto the project has been
divided into two phases. Phase I was to run on Diesel as the raw material and
Phase II on LNG. The appellant submits that consequentially LNG facility became
part and parcel of Phase II of a single project. Phase I was to have a capacity
of 695 MW and Phase II 1320 MW. The above would show, according to the
appellant that Phase II contemplated a substantial expansion in the generating
capacity vis-a-vis Phase I. Apart from the above, in the amendment letter the
Government imposed a condition that import of fuel (Diesel/LNG) for project
should not use infrastructure facilities of the Public Sector canalizing
agencies and the existing port infrastructure. Under letter dated 24.04.98,
Ministry of Industry confirmed that their approval is for
execution/implementation of an integrated project involving power project and
LNG regasification facility and associated infrastructure. Pursuant thereto DPC
applied to the Assistant Commissioner of Dapoli for registration of the Phase
II Power Project under the Project Import Regulation, 1986. In the above
letter, DPC had indicated that the material imported for power project and LNG
facility shall not be used for any other purpose. Therefore, according to the
appellant, even though the initial proposal to FIPB recognized the capability
of LNG facility for distributing gas, application for project import
registration categorically stated that the LNG facility will not be used for
any other purpose. The Government of Maharashtra, the sponsoring authority had
recommended grant of project import concession for the equipments required for
Phase II and also for LNG facility. Thus, according to the appellant, Phase II
with integrated LNG facility fully satisfied the conditions required for grant
of concessional rate of Customs duty applicable to power projects under Tariff
Item 98.01.
The appellant also refers to terms of the
Power Purchase Agreement (PPA) executed on 8.12.93 between DPC and Maharasthra
State Electricity Board (MSEB) in support of its contention on LNG facility.
The preamble to the agreement specifies that DPC will also construct facilities
for the receipt, storage and transmission of fuel to the power station. These
facilities include the single point, mooring and tankage for liquid fuel in
Phase I and a breakwater jetty and facilities for the receipt, storage and
regasification of LNG for Phase II.
The learned Sr. counsel who appeared on
behalf of the Revenue submitted that in the matter of deciding classification
Customs Department is the final authority and that the appellant cannot seek
shelter under the approval granted by FIPB or the recommendation of the
sponsoring authority. In support of the above proposition he placed reliance on
the decision of the Supreme Court in Jackson Thevara 1992 (61) ELT 343 (SC) = (2002-TIOL-213-SC-CUS) and the decisions of this
Tribunal in NALCO 1997 (94) ELT 409 = (2002-TIOL-138-CESTAT-DEL-LB) and EID Party 1991
(100) ELT 275(T). The Revenue would contend that LNG facility has been set up
to make available Natural Gas which is the raw material for various industrial
consumers including the Power Project. The equipment and material imported for
implementing processes before gas came into existence (including unloading
terminal, storage tank and regas terminal) cannot be regarded as equipment and
material imported for initial setting up of the Power Project or substantial
expansion of the existing Power Project within the meaning of Customs Tariff
Heading 9801. Strong reliance was placed by the learned counsel on the decision
of this Tribunal in NALCO wherein the port facility for unloading raw material
and loading finished goods was denied the project import benefit by a Larger
Bench of the Tribunal. It was further submitted that ratio of the decision in
Indian Charge Chrome 1991 (112) ELT 753 (SC) could not support the appellant as
it was contended. According to the Revenue the decision of Tribunal in Paradeep
Phosphates Ltd. 2000 (120) ELT 704 is no longer good a law in view of the
Larger Bench decision in NALCO. The decision of the Tribunal in TOYA
Engineering 2000 (122) ELT 315 was rendered under different facts and that the
decision is pending in appeal before the Supreme Court.
The Revenue would further contend that
LNG facility is required neither for initial setting up of Phase I of the Power
Project nor for substantial expansion of the existing unit. It only makes the
project more cost effective. Therefore, the goods imported for setting up LNG
facility cannot be brought within the purview of Customs Tariff Heading
9801.00(3). Equipment and material imported for setting up of LNG facility is
not directly used in setting up the power project. Therefore, it cannot be
treated as auxiliary equipment. This is the ratio of the decision of this
Tribunal in Punjab State electricity Board 1987 (27) ELT 432. An auxiliary
equipment required in connection with the substantial expansion is not covered
under Tariff Heading 9801. Therefore, according to the Revenue, the LNG
facility cannot be brought within the purview of the description given under
Customs Tariff Heading 9801.00 (3), nor can it be considered an integral part
of the power project.
On the second issue the Commissioner took
the view that a portion of the value of off-shore services contract is liable
to be added to the declared value of equipments under Rule 9(1)(b)(iv) of the
Customs Valuation Rules. The Commissioner took into consideration the following
facts.
The appellant had entered into four
contracts, two off-shore contracts and two on-shore contracts. Out of the two
off-shore contracts one relates to supply of equipment and machinery covered by
the off-shore supply contract and the other relates to supply of services
undertaken outside India covered by the off-shore services contracts. While the
contract value for supply of machinery and equipment for the LNG facility was
103.354 million US$ the contract value for service charges was 149.379 million
US$. Thus, the contract value for service charges for LNG facility would be
144.53% of the contract value for the machinery and equipment. In order to set
up Phase II of the power project, DPC entered into two off-shore contracts.
Off-shore supply contract for the supply of machinery was for 400 million US$
while the off-shore services contract for various services undertaken outside
India was for consideration of 10 million US$. Thus in respect of Phase II of
the Power project, the contract value for services charges was 25% of the
contract value for machinery and equipment Following are the additions made by
the Commissioner apportioning a portion of the service charges in respect of
different items. They are given below under three charts:-
OTHER THAN MARINE i.e. LNG TERMINAL
(Breakup of offshore services by Kvaerner)
|
No. |
Major Category |
Value for Services (Estimated) (US$) |
Amount included in the Assesable Value
as per Rule 9 (1) (b) (iv) of Custom Valuation Rules '88 (US$) |
|
(1) |
(2) |
(3) |
(4) |
|
1. |
Project Management |
10,356,519 |
10,356,519 |
|
2. |
Engineering Management |
6,731,736 |
6,731,736 |
|
3. |
Commercial Management |
2,589,129 |
2,589,129 |
|
4. |
Insurance |
800,000 |
NIL |
|
5. |
Engineering Studies |
2,507,435 |
2,507,435 |
|
6. |
Conceptual Detailed Layout |
9,193,927 |
9,193,927 |
|
7. |
Constructability |
417,906 |
417,906 |
|
8. |
Stress Analysis |
417,906 |
417,906 |
|
9. |
Test Procedures |
417,905 |
000 |
|
10. |
Commissioning Advisory Services |
2,925,341 |
000 |
|
11. |
Commissioning Plan |
2,089,529 |
000 |
|
12. |
Subcontractor Coordination and Supervision |
2,925,341 |
2,925,341 |
|
13. |
Contract and Legal |
417,905 |
000 |
|
|
|
41,790,579 |
35,139,899 |
MARINE WORK (Break-up of offshore
services by Six Construct Ltd.)
|
No. |
Major Category |
Value for Services (Estimated) (US$) |
Amount included in the assessable value
as per Rule 9(1)(b)(iv) of Customs Valuation Rules, 1988 (US$) |
|
(1) |
(2) |
(3) |
(4) |
|
1. |
Engineering Management |
2,128,000 |
* |
|
2. |
Commercial Management |
1,596,000 |
* |
|
3. |
Insurance |
532.000 |
000 |
|
4. |
Basic Engineering and Stability Calculations |
2,660,000 |
* |
|
5. |
Seismic Engineering |
1,330,000 |
* |
|
6. |
Detailed Engineering Design |
5,320,000 |
* |
|
7. |
Precast Factory Design |
1,330,000 |
000 |
|
8. |
Engineering for construction Methodology |
2,660,000 |
000 |
|
9. |
Specifying Equipment |
1,862,000 |
000 |
|
10. |
Scheduling |
1,330,000 |
* |
|
11. |
Mathematical Mooring Testing |
1,330,000 |
# |
|
12. |
Mathematical Wave Testing |
1,330,000 |
* |
|
13. |
Physical Model Testing |
1,862,000 |
000 |
|
14. |
Contract Administration and Legal support |
1,330,000 |
000 |
|
|
|
26,600,000 |
6,561,333.00 |
NOTE- @ 1/3 of the estimated value of the
service mentioned at Column (3)
#@ 100% of the estimated value of the services mentioned at Column (3)
Break up of offshore Services by the
Prime Contractor i.e. E.P.S.
|
Sr. No. |
Combined |
Value estimated (rounded to nearest
thousand (US$) |
Amount included in the assessable value
as per Rule 9(1)(b)(iv) of Customs Valuation Rules 1988 (US$) |
|
(1) |
(2) |
(3) |
(4) |
|
1. |
Sunk Development Costs |
2,600,000 |
* |
|
2. |
Coordination of preparation of Bid parameters, specifications,
RFOs |
1,772,000 |
* |
|
3. |
Evaluation of bids, selection of vendors, and review of
contracts and Purchase Orders |
972,00 |
* |
|
4. |
Inspection and quality Assurance |
5,934,000 |
* |
|
5. |
Offshore Warranty Coordination |
1,510,000 |
* |
|
6. |
Scheduling, Cost Engineering, Project Controls, reporting |
10,559,000 |
7821,051.30 |
|
7. |
Program and project Management |
8,221,000 |
* |
|
8. |
Regas Engineering Coordination Primary and Secondary Power |
1,031,000 |
# |
|
9. |
Regas Engineering Coordination-LNG Storage Tanks |
3,100,000 |
# |
|
10. |
Regas Engineering Coordination Civil, Site Roadways |
812, |
000 |
|
11. |
Regas Engineering Coordination Structural, Piping and fire
Protection |
1,738,000 |
# |
|
12. |
Regas Engineering Coordination Regas Process |
2,283,000 |
# |
|
13. |
Regas Engineering Coordination Controls Instrumentation and
Communications |
921,000 |
# |
|
14. |
Marine Engineering Coordination Breakwater |
1,034,000 |
000 |
|
15. |
Marine Engineering Coordination Jetty |
2,638,000 |
# |
|
16. |
Commissioning & Start-up Coordination |
541,000 |
000 |
|
|
Total |
45,666,000 |
35,093,417.20 |
Note *-@ 74.07% of the Service Charges
estimated at Column (3)
#-@ 100% of the Service Charges estimated at Column (3)
The Commissioner thus found that out of
the total Offshore Services contract dated 20th Nov. 1998 value of 115.672
Million US$, the amount of Services Charges worth 76,794.649.20 US$ are
includable in the assessable value. The amount of 115.672 US$ included the
estimated value of marine sub-contract services, namely, 1616000 US$. But no
part of the above amount was proposed by the Commissioner to be included in the
assessable value of the imported goods. All offshore and onshore contracts for
setting up LNG facility were amended on 28th April 2000. The amended value for
the offshore supply contract is 103.354 Million US$ and for the offshore
services contract is 149.376 Million Us$. In the absence of information on the
item-wise increase in the value of services, Commissioner took the view that it
is reasonable to apply the pro rata method. He came to the conclusion that out
of amended total value of Us$149.37 million worth of services 99.170724 Million
US$ worth of services is includible in the assessable value of the imports. For
the purpose of determining the transaction value of the goods for setting up
the LNG facility in terms of Rule 4 read with Rule 9(1)(b)(iv) a loading @
95.95% of the declared value was directed to the made.
The Commissioner further observed that
there is no clear indication available in the contract or any other document as
to how service charges for different elements have to be apportioned. The
apportionment will have to be made in a reasonable manner appropriate to the
circumstances and in accordance with the generally accepted accounting
principles. Reliance was placed on a Customs Cooperation Counsel (CCC)
Technical Committee Case Study 1.1 which dealt with the treatment of assists
like engineering, development etc. The payment for plans drawings etc. was made
for four plants, while the imported goods were used for setting up only one
plant. The case study determined the Customs Value by adding one quarter of the
total payments for the drawings and plans, by apportioning one fourth liability
for the imported plant, since three other plants were manufactured on the basis
of same plans and designs. Reliance was also placed on the decision of the
Supreme Court in Essar Gujarat (1996 (88) ELT 609). In the above case the Apex
Court held as follows:
"Since there is no clear indication
as to how the various services have been valued separately, 10% of the amount
of DM 23,100,000 should be added to the value of the plant on this
account".
The appellant would contend that offshore
services contract is not related to offshore supply contract. No part of the
value of the services contract is includible in the value of imported
equipments since imported equipment was not manufactured according to any
drawing or design, developed under the services contract and made available to
the manufacturer/supplier of the equipments. The appellant would intimate the
required specification to the prospective suppliers who would manufacture the
goods as per the specification. According to the appellant, making available
specification is outside the purview of Rule 9(1)(b)(iv). The Ld. Counsel for
the appellant referred to "Customs Valuation-Commentary on the Gatt
Customs Valuation Code" by Saul L. Sherman and H. Glashoff. The relevant
portion from para 117 book is extracted below:
"Detailed specifications including
various dimensions noted on a drawing of the machine, are included inn the
buyer's order, so as to advise the exporters/manufacturer of what the buyer
needs. The cost of engineering and drawing are not part of customs value, even
if undertaking outside the country, to which the machine is shipped, to the
extent that they are an appropriate way of ordering the machine, - i.e., of
telling the manufacturer the specifications of what is being ordered."
The unloading arms are not items
manufactured according to any drawing made available by the appellant. They are
standard items manufactured according to the drawings and designs of the
equipment suppliers. As mentioned earlier the appellant had provided only the
required specifications. Reliance placed by the Commissioner on Clause 2.5 of
the document "Instruction to Vendors" relating to unloading arm is
misplaced. The appellant would submit that such a provision for review is
provided only to ensure that manufacturing drawing prepared by the vendor is in
fact according to the specifications. The appellant relies on the following
provisions in the data sheet in support of its contention that specification
provided by it would not amount to engineering design for manufacture or
unloading arms:
"C.21 Article 4 specifically
provides as follows:
'Unloading arms shall be vendors standard
design, which has a proven track record.'
C.22 Article 5.3 also makes this clear
and is reproduce below:
'The supply shall include the testing,
fabrication, Shop Erection, testing, certification, documentation and packing
in accordance with the data sheets, specifications and other documents as
referenced in the material requisition."
C.23 Article 7.1.1 dealing with the testing
requirements is also important:
'The design, engineering and manufacture
of unloading arms shall be as per vendors standard Marine type for LNG service,
meeting of technical design requirements as specified in this specification and
any documents referenced herein.'
C,24 Article 7.1.3 is also important:
'The intention of this specification is
to minimize the purchaser's involvement in the detailed design of the unloading
arms. It relies on the skill and experience of the vendor in the design and
packing of LNG unloading arms, in environments similar to that specified in the
Dabhol terminal. It is intended that the equipment is as close to the vendors
standard as possible, while maximizing the use of components proven in LNG
service.'
C.25 Article 7.10.1 dealing with
materials specifies that 'all materials used shall be vendors standard,
suitable for LNG service and the marine environment of Dabhol.'
C,26 Article 12.1 dealing with the
documentation provides as follows:
'Relevant drawings and documentation
shall be provided by the vendor in accordance with the requirements of the
purchaser's Vendor Document Requirement Schedule (VDRS), which forms part of
the requisition.'
The appellant would further contend that
no data is provided by the offshore contractor as an assist necessary for
production of steel plants required for fabricating the tanks. The role of the
offshore service contractor was limited to determining the pressure,
temperature and other parameters of the LNG at different parts of the tank and
from these data arrive at the thickness of the steel sheets / plants required
for different portions of the tank. The manufacture of the steel plates is not
as a result of identifying the thickness or quantity. The design, fabrication
and construction etc. of the LNG storage tank at Dabhol site referred in
Article 1.1.1 is out of standard imported material like Ally/carbon steel
plate. The detailed drawings developed by the contractor are of the tanks to be
constructed in India. These drawings and design of the tank are reviewed by the
service contractor. There is no drawing or design prepared by the
manufacture/supplier of the 9% nickel steel plate/carbon steel plate. These are
manufactured according to the normal production process of the steel mills and
supplied in the specified quantities and dimensions. Therefore, according to
the appellant in respect of the above item also no addition could be made under
Rule 9(1)(b)(iv).
The marine work takes in construction of
breakwater, dredging and LNG Jetty. Equipment under import in the circuit LNG
Jetty are foundation piles, steel profiles fenders, mooring systems,
navigational aids etc. The Commissioner had included only those service charges
which according to him related to imported goods meant for the jetty. It is
contended on behalf of the appellant that the nature of the service rendered by
the sub-contractor Six Construct Limited, is such that its value is not
includible. Therefore, the assumption that one third of the value of the
services under this heading should be added to the transaction value of the
imported equipment is incorrect. The appellant submits that the service
rendered under the Heading 'Engineering & management does not at all
involve identifying any specification for any equipment or material required
for marine works. It relates to cost to Six Construct Limited for planning,
directing, controlling, evaluating the activities in order to accomplish the
task. Under the Heading 'Commercial Management' the service provider has
covered its cost of commercial management and coordination of financing,
management taxes and duties, insurance services, currency management etc. It
has no connection to the services contemplated under Rule 9(1)(b)(iv). As far
as Heading 'Detailed Engineering Design' is concerned, the appellant would
contend that imported items for the Jetty are readily available articles such
as plies, fenders, mooring systems, navigation aids etc. which do not require
any design or engineering drawing supplied by the purchaser. The Basic
Engineering and Stability calculation is an activity which precedes detailed
engineering and therefore, its has also no connection to the services
contemplated under Rule 9(1)(b)(iv). Seismic Engineering is something related
to the site in India which also does not involve any engineering required for
production of imported goods. This service rendered under Heading 'Scheduling'
is in respect of an overall project schedule for implementation of project
execution. It contemplates targets for completion and progress on monthly
basis. The service has also no relevance under Rule 9(1)(b)(iv). According to
the appellant to the appellant, the service rendered under Mathematical Mooring
Testing is also not connected with any engineering design specification. The
services rendered under Mathematical Wave Testing relates to determination of
design parameters at the berth and along the trestle. it is part of jetty work
which is mostly a concrete construction utilising materials purchased in India.
The appellant would, therefore, submit that addition made by the Commissioner
in respect of the activities undertaken under the marine work is unsustainable.
According to the appellant, none of the
services by prima contractor involved any preparation of specifications nor any
engineering. Each of those items related to the coordination of the various
works of marine and LNG terminal. The services under the Heading 'Sunk
Development Costs' was in relation to developing various methodologies of
implementing the project and choosing one of such alternatives. It is not
identical with the term 'development' as understood in the context of ‘Research
& Development'. According to the appellant prima contractor's service did
not at all involve any engineering or specification r review of drawings. It
relates only to coordination with various sub-contractors entrusted with the
execution of other works.
On the issue of includibility of
different elements of services charges in the value of imported goods for LNG
facility under Rule 9(1)(b)(iv) of the Customs Valuation Rules, 1988, the Ld.
Senior counsel addressed arguments in support of the finding of the
Commissioner. According to hi, following are the relevant conditions for
inclusion of the value of services in the value of the imported goods under
Rule 9(1)(b)(iv):
(a) The value of the
services has not already been included in the price actually paid or payable
for the imported goods.
(b) The services were
supplied directly or indirectly by the buyer free of charge.
(c) The services have
to be undertaken elsewhere than in India.
(d) The subject
services fall in any of the categories like engineering,
(e) The services were
supplied by the buyer 'for use in connection with the production and sale for
export of the imported goods' (emphasis supplied).
(f) The services are'
necessary for the production of the imported goods' (emphasis supplied).
There is no
dispute regarding the first three conditions being present in this case. But
according to the appellant the facts would not satisfy condition (d) to (f)
since the services rendered relating to identifying the specifications do not
fall in any of the category of services described in Rule 9(1)(b)(iv). The Ld.
Senior Counsel would submit that identification of the specification is also
very much part of the engineering and drawing. He quoted the following by
Sherman and Glashoff relied on by the appellant:
"The cost of engineering and drawing
are not part of the Customs value, even if undertaken outside the country to
which the machine is shipped to the extent that they are an appropriate way of
ordering the machine-that is, of telling the manufacturer the specifications of
what is being ordered. Only if the engineering or drawing goes further, should
it be deemed to be a part of the production process" (Emphasis supplied.)
Reliance was placed by the Ld. Counsel on
the decision of the Supreme Court in Andhra Petro Chemicals (APCL) 1997 (90 ELT
275 (SC) = (2002-TIOL-43-SC-CUS). In the above case as
similar plea that the supplier had given only specification to the sub-vendor
to conform to the operational requirements of the equipment was taken. The
Tribunal took the view that these charges for specifications are to be included
in the value of the goods. The above decision was upheld by the Hon'ble Supreme
Court.
Revenue contends that the imported goods
are tailor-made for the state of art LNG facility utilizing cryogenic
technology. The processes involved for setting up the LNG facility are unique
to Dabhol, and are confidential information. Therefore, an unconnected vendor
will not be able to supply the goods unless the process and the associated
drawing and engineering specifications, whether patented or not, are forwarded
to the vendor. The Ld. Counsel points out that reference to the instructions to
vendors (ITV) would clearly show the involvement of the service contractor in
detailed designing of unloading arms. The coordinated activities between vendor
and the offshore service contractor/sub-contractor shows continuous interaction
between the service contractor and the vendor till the design/drawing is
finalized. Service contractors/sub-contractors review the drawing submitted by
the vendors and thus assist the vendor in the process of the imported goods.
According to the Revenue, the LNG storage
tanks are imported in disassembled form which have been assembled/erected at
the site after importation. The imported items are not steel plants
simpliciter, but they are identifiable parts of the storage tank. The drawings
submitted by DPC prepared by the service sub-contractor for LNG storage tank,
it was shown that the cylindrical walls of the tank is divided into eleven
cylindrical trips each of width 3391 mm. Each strip has been referred to as a
course. Each course is divided into curved plates called as shell plates. 24
shell plates when joined together will make one course. Eleven such courses
make up walls of the tank. Service contractor/sub-contractor has prepared
detailed drawings of tanks as well as plates under import. On the basis of
these drawings, the vendor has manufactured the plates. It can, therefore, be
seen that when moves form bottom of the tank towards the top, the thickness of
the shell decreases. The invoice dated 21.2.2000 pertaining to Bill of Entry
No.566 dated 1.3.2000 would clearly show that the plates were manufactured as
per the details shown in drawing No. 69 B 02 MF 0004.
According to the Revenue the scheme of
the contracts is designed in such a manner that engineering is divided between
the service contractor and the vendor depending upon the experience of the
vendor. The service contractor had supplied, inter alia, the following
documents to the vendor:
(i). Material requisition including P
& Ids, Block diagram of the equipment.
(ii). Instruction to vendors (proves
process of review and inter action)
(iii). Data Sheets (Dimensions of arms)
(iv). Specification of 'unloading arms'
(General Instructions).
P & ID diagram is a drawing which
shows details of the concerned equipment and their inter connection with other
equipment for a particular portion of the LNG facility. Block Diagram is a
diagram which shows the general details of equipment and its interconnection
with other equipments. The above mentioned documents are passed on to the
vendors only for the reason that these documents are necessary for the
production of the imported goods. ON the basis of the above mentioned diagrams,
the vendor had developed P & Ids and manufacturing drawing of the equipment
which are further reviewed by the service contractor. Therefore, the activities
undertaken by the service contractor/sub-contractor are necessary for the production
for the production of the goods. According to the Revenue the Commissioner was
fully justified in making the additions and the appellant's case both on the
issue of classification and valuation is only to be rejected.
Appeal Nos. C/520/2000-NB (A) & C/519/2000-NB
(A)
In these lapels at the instance of DPC
and Revenue challenge is against the order passed by the Commissioner (Appeals)
dated 26.6.2000. The Commissioner (Appeals) took the view that Single Point
Mooring System (SPM) is part and parcel of the project and therefore, the goods
imported for setting up will have the benefit of concessional rate of duty
under Project Import Regulations. In coming to the above conclusion the
Commissioner (Appeals) has referred to the restrictions imposed by the Government
of India on the appellant that it will not use the infrastructure facilities of
Public Sector Canalizing agencies and existing port infrastructure in the
import of fuel. Commissioner (Appeals) thereafter observed that in the light of
the restrictions imposed by the Government DPC have not other go but to put up
SPM system to proceed with the project. Under these circumstances, the
Commissioner (Appeals) took the view that SPM would become part and parcel of
the project. He had also noted the fact that SOM has been treated as part of
the project approved by various sponsoring authorities. It was registered in
December 1996 as such without any objection. He took the view that SPM system
cannot be compared to the usage of vehicles in transportation of goods to the
project. Even after IInd phase SPSM system qualifies for project import as an
auxiliary system.
It is contented by DPC that once the
Commissioner came to the conclusion that SPM was part and parcel of power
project, no question would arise for further examining the role of SPM in the
second phase. SPM is basically required for the first phase of the project. SPM
was one of the items of machinery included in the list submitted by the
sponsoring authority to the Central Excise & Customs, Pune. Therefore, the
above mentioned direction given by the Commissioner is totally extraneous and
irrelevant. Apart from the above, it is submitted by DPC that role of SPM in
the second phase of the power project was neither raised in the show cause
notice nor in the original order of the Assistant Commissioner. Under these
circumstances, the Commissioner could not have enlarged the scope of the
enquiry by a direction in the order of remand. The appellant would further
submit that even after second phase was commissioned the appellant would still
require to maintain SPM system to ensure supply of Naphtha or Distillate as
back up fuel or/to commission or start the power plant after it was shut down
for any reason. According to the appellant, SPM facility was not a temporary
facility. Even if the SPM system is not to be used at Phase II stage, it cannot
be denied the benefit of Heading 9801.
The contentions raised by the Revenue in
its Appeal No.C/520/2000 are similar to those in the case of LNG facility in
the appeal filed by DPD. It is contended that SPM system cannot be treated as
part and parcel of the project and neither auxiliary equipment of the project.
The Ld. Counsel for the respondent supported the finding of the Commissioner
(Appeals) on the basis of the arguments addressed by him in Appeal
No.C/601/2001-NB (A).
We will first consider the issue whether
various items of machinery equipments etc. imported for LNG facility are
entitled t concessional rate of Customs duty under Tariff Item 9801.00 as
Project Import. The Revenue is seeking to support the finding of the
Commissioner against the assessee relying on larger Bench decision of this
Tribunal in NALCO. Appellant on the other hand would contend that the facts of
the present case are more akin to the facts of Paradeep Phosphates Ltd. and
also Toyo Engineering. In NALCO the Larger Bench took the view that supply of
equipments for port facility at Visakhapatnam cannot be considered as equipment
imported for initial setting up of a unit or substantial expansion of existing
unit of an industrial plant. Unloading raw material at the port or even at the
plant may be necessary for the activity of manufacture or process in an
industrial plant, but that cannot be treated as equipment required for the
initial setting up of a unit or for substantial expansion of an existing unit
which is a required condition for being treated as project import under Item 1
(D)(1) of Heading 84.66. On going through the facts in the NALCO case, we find
that contention raised by the Revenue was that the project in the case
consisted only of extraction of aluminum ore and manufacture of alumina and
port facility system had nothing to do with the mining operation or manufacture
of alumina and it was situated miles away form the former.
The facts in Paradeep Phosphates Ltd. are
slightly different. It was held that a captive berth for import of raw material
is required in connection with setting up of fertilizer project. Mobile
Continuous Ship Unloader completely assembled was registered under Project
Import Regulations, 1986. Rejecting the contention taken by the Revenue that
the ship unloader was not an integral part of the project import for
manufacture of fertilizer project, the Tribunal took the view that imported
machinery would appropriately be covered by the expression 'auxiliary
equipment' mentioned under Heading 98.01. The Tribunal took note of the fact
that construction of captive berth for import of raw materials was part of
setting up of the fertilizer project.
We now examine the LNG facility. It was
being treated as part of the Power Project by the parties to the agreement.
Appellant has placed reliance on item 4 of the term sheet filed along with the
memorandum of understanding (MOU) which reads as follows:
"4. Power Plant
Assumed 2000-2400 MW nominal capacity;
Plant will be designed as a combined
cycle facility including gas turbines, steam turbines, heat recovery steam
generators, demineralized water plant, cooling tower(s), 400 MW substation fuel
storage to accommodate 30 days light oil storage (collectively, the 'Power
Plants')
Project includes construction of
regasification facilities for LNG and pipeline interconnections to Power Plant
(collectively, the 'Gas Facilities')"
In the letter dated 3.2.93 the FIPB
convoyed the approval of the Government of India to the setting up of the power
project at Dabhol. The relevant portion is quoted below it is seen that -
"Set-up,
own and operate a Natural Gas fired combined cycle power station of a capacity
of 1920 MW (the capacity may be extended to 2550 MW at a future date), based on
imported Liquefied natural Gas (LNG) along with an integrated facility for
sourcing, import, reception, handling, storage and regasification of LNG, for
fuel supply to the power station."
Even when the project was divided into
two phases, LNG facility was part of the project. In the letter dated 23.3.94
FIPB, while approving the modification of the project into two phases, a
condition was imposed that the infrastructure facility of the Public Sector
canalizing agency and the existing port infrastructure should not be used for
import of fuel (Diesel/LNG). Such a condition is not available in NALCO. There
is merit in the contention of the appellant that when such a condition was
imposed, in this case, LNG facility, including regasification facility, was to
be treated as part of the integrated project. In reply to the letter dated
31.8.98 addressed by Enron International, Ministry of Industry vide letter
dated 24th September 98 confirmed that the integrated project involved power
plant, LNG regasification and associated infrastructure. It is in this
background DPC applied to the Assistant Commissioner of Customs, Dapoli for
registration of Phase II of the Power Project under Project Import Regulation
1986.
There cannot be any dispute on the legal
position that it is the Customs authorities who are competent to arrive at a
decision regarding classification of the goods not withstanding any view taken
by the licensing authority. But we are referring to the correspondence between
the parties as above and terms of agreement only to examine whether the
regasification of LNG for fuel supply to the power plant was part of an
integrated project so that import made for LNG facility would come under
sub-heading 9801.00. If regasification facility is port of the integrated
project, then import of equipment etc. in connection with LNG facility will be
entitled to the benefit of project import, as was held in Paradeep Phosphates
Ltd. and such a conclusion would not be against the ratio of NALCO also.
Taking into consideration the entire
material before us we are inclined to take the view that LNG facility is part
of the integrated power project and therefore, various items of machinery and
equipment imported for LNG facility are entitled to concessional rate of
Customs duty under Tariff Item 9801.00 as project import.
In this context, it may not be out of
place to refer to the settlement arrived at between the parties in NALCO while
their appeal against the decision of this Tribunal was pending before the
Supreme Court. Civil Appeal No. 6902-6906/97 filed by NALCO was disposed of by
the Hon'ble Supreme Court on the basis of the Settlement by order dated
10.3.2004. When this order was reported as 2004 (167) ELT A96. We reposted the present
appeals which were reserved for orders and heard both sides. It was submitted
before us that the issues arising in NALCO were not decided by the Hon'ble
Supreme court on merits. The order of the Hon'ble Supreme Court reads as
follows :
"Application has been filed
indicating that the matter in this dispute has been settled between the parties
and a Committee on Dispute has ultimately taken the view that the Equipment
connected with the storage of caustic soda and alumina can be considered as
part of manufacturing process and project import benefit could be considered
for these equipment as mode of settlement. Other than the above equipment all
other equipment of part facilities should be considered as port handling
equipment and thereof, could not be eligible for project benefit.
In view of this settlement the impugned
order under appeal is set aside and is ordered in terms of the settlement. The
appeal stands disposed of accordingly.
The learned counsel appearing on behalf
of the Revenue brought to out notice the minutes of the meeting of the
Committee on Disputes held on 17.2.2004 which would show that the Department of
Revenue has agreed to the terms of agreement without prejudice to their right
in any other case on similar issue. Therefore, the settlement may not be taken
as an admission on the part of the department regarding the legal position. We
may point out that the view taken by us, the eligibility for concessional rate
of duty as project import, is on the basis of the facts in the present case and
the contentions raised by both sides.
Now we come to the issue on valuation.
The total value of the offshore service charges would come to 149 million US$.
The assessee contended that no part of the service charges is addable to the
value of the imported goods since offshore service supplied has not relation to
the manufacture of the goods imported and that a portion of the service charges
related to post importation activity. The Commissioner took the view that
amount of 99 million US$ of service charges would be relatable to the
manufacture of imported goods and therefore, includible in the value of goods
in terms of Rules 9(1)(b)(iv) of the Customs Valuation Rules, 1988.
It is relevant to note that permissions
was granted to Enron Power Corporation to set up, own and operate a natural gas
fired combined cycle power station at Dabhol. for the above purpose joint
venture company known as Dabhol Power Company was formed by Enron, Maharastra
State, Maharastra State Electricity Board and General Electric Corporation. DPC
entered into off-shore contract with Enron Equipment Procurement Company
(EEPC). While the value of supply of machinery and equipment for LNG facility
under the above contract was 103.357 million US$, the contract value for
service charges was 149.376 US$. It is thus noticed that the contract value of
service charges for LNG facility is 144.53% of the contract value of machinery
and equipment. In respect of Phase II of the power project the off-shore
contract was with M/s. General Electric, Japan Ltd. and its value was 400
million US$. The off -shore service contract was with Bechtel Overseas
Corporation, Enron Power Services BV and GE Power Systems Inc. The value of the
various service contracts referred above was 100 million US$.
The main contention raised by the
assessee-appellant is that only 'specification' is provided under the service
contract and it can, in no way be, brought under Rule 9(1)(b)(iv). No
engineering drawing is being given under the offshore service contract on the basis
of which manufacture of different items had taken place. On the other hand, the
Revenue would contend that what has been provided under the offshore service is
much more than the specification. If it is beyond the specification, then the
ratio of the decision of the supreme Court in Andhra Petro Chemicals Vs. CC,
Madras. 1997 (90) ELT 275 (SC) = ((2002-TIOL-43-SC-CUS) would apply. Therefore, we
have to examine in this case whether on the facts the offshore service contract
provided much more than specification so that it would amount to design and
engineering to enable production of the goods imported. In Andhra Petro
Chemicals Ltd. Vs. CC Madras 1997 (90) ELT 349 (SC) the decision of the
Tribunal was affirmed by the Supreme Court. On going through the decision of
the Tribunal which is reported as Andhra Petrochemical Ltd. Vs. CCE, Madras
1997 (91) ELT 349 we find two relevant factors - (1) Davy Mekee (London) Ltd.
Entered into contract with M/s. APCL for supply of equipment and material, for
technical know-how and for servicing of the plant propose to be erected. DML
supplied detailed specifications for each item, standards and data sheets as
listed on the engineering document list, general design requirements, layout
and other relevant technical information while placing the purchase orders on
the manufacturers. (2) the drawing submitted by the manufacturers were required
to be reviewed and approved by DML . Equipment was required to be inspected by
DML. Invoices by the manufacturer were raised on DML. In turn DML raised
invoices on APL. It was contended on behalf of the appellant that the DML had
not taken up themselves any responsibility for providing designs etc. necessary
for the production of the imported goods and that the responsibility of DML
confined to providing know-how and front end engineering package of the plant
at Vizag. The Tribunal took the view that the services rendered towards
engineering design, work plans, sketches etc. undertaken by the DML elsewhere
than in India were necessary for the projection of the imported goods got
manufactured by DML and supplied to APL and therefore, the value of the
services are covered by the provisions of Rule 9(1)(b)(iv) of the Customs
Valuation Rules.
EPS, the off-shore service contractor has
engaged two major sub-contractors-Six Construct Ltd. (SCL) for marine work and
Kvaerner Dabhol LNG joint venture (KJV) for LNG Terminal. Apart from the above,
EPS as a prime contractor has also provided services in terms of Off-shore
Services contract. Clause 3.0.1 of Pr. CP would show that EPS and KJV are
assigned the job of offshore engineering. Clause 1.2.2. of PRCP makes it clear
that EPS and KJV are responsible for Project Management and Engineering
(Offshore). Clause 2.1 would further sow that EPS ; is to supply Lump Sum Turn
Key facility covering design, engineering, procurement, construction and
commissioning. Clause 2.2 makes it the responsibility of KJV for the facility
covering, inter alia, All Design and Engineering Process, Design, Tankage
Envelope, Civils, Site Preparation, Process Area, Jetty Top Sides, Pipework
Corridor, and preparation of specification and procedures for design,
construction, testing and commissioning. 'Quality Plant for Design and
Procurement' also would show that the design and engineering taken by offshore
service contract is in the form of drawings, specification, calculations,
mannuals etc. The equipment designed by the vendors/manufacturers on the basis
of design and engineering specifications provided by the service contractor is
also subject to review and control by service contractor. An examination of
Instructions to Vendors (ITV) would make it further clear that the details of
the design are subject to review and modification by the service contractor.
Service Contractor has to provide date sheets and drawings to the vendor. In
the nature of the different part to be manufactured, it is evident that an
unconnected vendor without such data sheets and drawings from the service
contractor cannot manufacture the imported goods. The above mentioned documents
would clearly show that the manufacture of the goods imported requires
coordinated activity between the vendor and offshore service
contractor/sub-contractor. There is continuous interaction between them till a
design/drawing is finalized.
The instructions to vendor would also
show that the vendor has to submit calculations, performance and materials,
engineering data and certification and manufacturing date dossier for review of
the offshore service contractor in addition to the date sheets and drawings.
Therefore, the offshore service contractor in addition to providing design and
engineering specifications to the vendors, has assisted not only in the
development of manufacturing drawing of the imported equipment but also in the
development of manufacturing date dossier of the project.
The Piping and Instrumentation Diagrams
(P & ID's) developed by the service sub-contractor are essential in the
further development of drawings by the vendor for the manufacture of LNG
unloading arms. Such drawings are not limited for the purpose of erection
alone.
In the case of LNG storage tank also, the
contention raised by the appellant that the service contractor gives only
specifications is not seen correct. Detailed design and drawings were provided
by the service contractor in respect of every part of the storage tank. The
material requisition, date sheets and drawings of the tank would clearly show
that the service contractor had intimated the vendor about the complex
requirement of production of the plates. Without such design and drawings the
vendor could not have produced and supplied the required plates etc. for the
storage tanks. Similarly, in respect of other equipment like BOG condensers,
compressors, LNG vaporisers etc. there had been continuous interaction between
service contractors an vendors in finalizing the drawings required for the manufacture.
The Commissioner has correctly held that no unconnected vendor/manufacturer
could have manufactured equipment and materials for LNG facility, which is
based on state of art technology, without the help of these assists provided by
the importer i.e. DPC through the service of the contractor like KJV and SCL.
The Commissioner has correctly relied on the ratio of the decision in the case
of Andhra Petrochemicals Ltd.
In relation to marine work also it is
seen that the service contractor had provided considerable support by design
and engineering. Equipments which were imported in respect of LNG Jetty are
foundation piles, steel piles, steel profiles, fenders, mooring systems,
navigational aids etc. From the scope Book for the Marine Work it is seen that
considerable engineering has to be undertaken to arrive at the specifications
of piles, steel profiles, mooring systems, fenders etc. the depth to which the
piles are to be installed, load on the piles including the load of the
pre-stressed concrete beams and pipelines etc. are all to be taken into
account. It cannot be contended that standard production by the sellers would
serve the purpose. Therefore, a part of the service charges relating to the
marine Work is also liable to be added to the imports made in connection with
the above work.
On going through different items coming
under each category, we find that some of services may not have any impact at
all on the production of the goods imported. For example, under the heading
'Other than marine i.e. LNG Terminal', Item 3 Commercial management and item 7
Constructability. The value of these services have nothing to do with the
production of the goods imported and therefore cannot be included in their
assessable value. We are also of the view that in respect of Items 1, 2, 6, 8
and 12 the entire value of service contract cannot be added to the assessable
value of the goods imported. About 50% of the value can be estimated as that
will be relatable to the equipments imported. In the result, the amount of the
value of the services to be included in respect of import relating to other
than Marine i.e. LNG will have to be modified as follows :
|
Sl. No. |
Major Category |
Value for Services (Estimated |
Amount included in the impugned order |
Amount required to be included and
Basis |
|
|
|
|
|
|
Basis |
Amount |
|
1. |
Project Management |
10356,519 |
10,356,519 |
50% |
5,178,260 |
|
2. |
Engineering Management |
6,731,736 |
6,731,736 |
50% |
3,365,868 |
|
3. |
Commercial Management |
2,589,129 |
2,589,129 |
0% |
- |
|
4. |
Insurance |
800,000 |
- |
0% |
- |
|
5. |
Engineering Studies |
2,507,435 |
2,507,435 |
100% |
2,507,435 |
|
6. |
Conceptual Detailed layout |
9,193,927 |
9,193,927 |
50% |
4,596,964 |
|
7. |
Constructability |
417,906 |
417,906 |
0% |
- |
|
8. |
Stress Analysis |
417,906 |
417,906 |
50% |
208,953 |
|
9. |
Test Procedures |
417,905 |
- |
0% |
- |
|
10. |
Commissioning Advisory Services |
2,925,341 |
- |
0% |
- |
|
11. |
Commissioning Plan |
2,089,529 |
- |
0% |
- |
|
12. |
Sub Contractor Coordination & Supervision |
2,925,341 |
2,925,341 |
50% |
1,462,671 |
|
13. |
Contract & Legal |
417,905 |
- |
0% |
0 |
|
|
|
41,790,579 |
35,139,899 |
|
17,320,150 |
In the case of offshore service by Six
Construct Ltd. we find Item No. 2,5,10 and 12 are not relatable at all to the
equipments imported. In respect of Item Nos. (1), (6) and (11) we hold that
only 50% of the amount included by the Commissioner could be includible. As far
as Item 4, namely Basis Engineering and Stability Calculation is concerned, we
upheld the amount included by the Commissioner. In the result, the amount that
has to be included in respect of offshore service in respect of Six Contruct
Ltd. would be as follows :
|
Sl. No. |
Major Category |
Value for Services (Estimated |
Amount included in the impugned order |
Amount required to be included and
Basis |
|
|
|
|
|
|
Basis |
Amount |
|
1. |
Engineering Management |
2,128,000 |
709,333 |
50% |
354,667 |
|
2. |
Commercial Management |
1,596,000 |
532,000 |
0% |
|
|
3. |
Insurance |
532,000 |
- |
0% |
- |
|
4 |
Basis Engineering & Stability Calculations |
2,660,000 |
886,667 |
100% |
886,667 |
|
5. |
Seismic Engineering |
1,330,000 |
443,333 |
0% |
- |
|
6. |
Detailed Engineering Design |
5,320,000 |
1,773,333 |
50% |
886,667 |
|
7. |
Precast Factory Design |
1,330,000 |
- |
0% |
- |
|
8. |
Engineering for Construction Methodology |
2,660,000 |
- |
0% |
- |
|
9. |
Specifying Equipment |
1,862,000 |
- |
0% |
- |
|
10. |
Scheduling |
1,330,000 |
443,333 |
0% |
- |
|
11. |
Mathemetical Mooring Testing |
1,330,000 |
1,330,000 |
50% |
665,000 |
|
12. |
Mathematical Wave Testing |
1,330,000 |
443,333 |
0% |
- |
|
13. |
Physical Model Testing |
1862,000 |
- |
0% |
- |
|
14. |
Contract Administration & Legal Support |
1,330,000 |
- |
0% |
- |
|
|
|
26,600,000 |
6,561,333 |
|
2,793,000 |
For Marine Sub-contractor Services total
value would come to 1616000 US$ out of which no portion was added by the
Commissioner to the assessable value of goods imported. We do not propose to
make any deviation on this aspect.
On the above basis the percentage of
addition to be made would be as follows :
|
|
Estimated Value for Services |
Amount required to be included |
|
LNG Terminal |
41,790,579 |
17,320,150 |
|
Marine Works |
26,600,000 |
2,793,000 |
|
Marine Subcontractor Services |
1,616,000 |
|
|
Total |
70,006,579 |
20,113,149 |
|
|
|
28.73% |
By applying the above ratio, out of the
estimated value of45666000 US$ of Services in respect of Offshore Services by
the Prima Contractor the amount to be included in the assessable value of goods
would be 13,120,011 US$. Prime Contractor Services cover both LNG Terminal and
Marine Works.
Now we will consider the enhancement
consequent to the amendment to the agreement on 28th April 2000. The original
value of offshore service at US$ 115.672 million was enhanced as US$ 149.376
Million. Out of the additional value of US$ 33.704 Million only a portion is
relatable to equipments. Therefore, by applying the ratio of 28.73% the amount
to be included in the assessable value will be as follows :
|
S. No. |
Major Category |
Value of Service (Estimated) |
Amount of be included |
|
1 |
2 |
3 |
4 |
|
1 |
Acceleration costs |
5,652,174 |
|
|
2 |
Geotechnical issues |
16,596,996 |
|
|
3 |
Contract Variations |
11,455,260 |
3,291,139 |
|
|
Total |
|
3,291,139 |
Thus out of the total value of US$ 149.37
Million Worth of Services, 36,524299 MUS$ worth of Services has to be included
in the assessable value as follows :
|
S. No. |
Major Category |
Amount to be included |
|
A |
LNG Terminal |
17,320,150 |
|
B |
Marine Works |
2,793,000 |
|
C |
Marine Subcontractor Services |
|
|
D |
Services by Prime Contractor |
13,120,011 |
|
E |
LNG Offshore services contract : Ombibus Geotechnical and
Variation settlement agreement |
3,291,139 |
|
|
Total value of additions to be made |
36,524,299 |
The Commissioner took the view that on
the issue of claiming project import benefit there has been no mis-declaration
warranting confiscation under Section 111(m) of the Customs Act and therefore
penal provisions of Section 111(a) are not to be invoked. In respect of
mis-declaration of value of the goods that Commissioner took the view that the
impugned goods are liable to confiscation under Section 111(m) of the Customs
Act. He also held that penalty under Section 112(a) has to be imposed.
On the issue of confiscation, imposition
of redemption fine and penalty we are inclined to accept the contention raised
by the appellant. It is contended that the existence and the scope of offshore
services contract were in the knowledge of the department, that in fact the
first Bill of Entry was assessed by including the value of offshore services
contract in the value of imported pipes. Apart for the above, since this is a
case where provisional assessments were finalized, no penalty is liable to be
imposed. In view of the above, we set aside that portion of the order of the
Commissioner directing confiscation of the goods, imposition of redemption fine
and penalty.
The assessments will be finalized taking
into consideration the finding in this order on the eligibility to claim for
concessional rate of Customs duty under Tariff Item 9801.00 as project imports
and the quantum of value of offshore services contract to be added to the
declared value of the equipments under Rule 9(1)(b)(iv) of the Customs
Valuation Rules 1988.
Appeal Nos. C/519/2000 and C/520/2000
For the reasons we have already recorded
while considering Appeal No. C/601/2000 we agree with the view taken by the
Commissioner that the imports relating to SPM system are to be treated as
Project Import under 9801.00 entitling concessional rate of duty. The direction
given by the Commissioner to the Assistant Commissioner for further
investigation is vacated. The Assistant Commissioner will proceed to finalize
the provisional assessments on the above basis.
In the result, Appeal No. C/601/2001
filed by DPC stands partly allowed. Appeal No. C/519/2000 filed by DPC is
allowed and the Appeal No. C/520/2000 filed by the Revenue is dismissed.